Last updated · 2 min read
FAA Part 5 Explained: What the SMS Rule Contains
By Michael Sidler, Founder, RISE
This article explains published regulations and is not legal or compliance advice. See the linked sources.
Verify against the current regulation at the primary source.

14 CFR Part 5 is the FAA's safety management system rule. It sets out who the rule lists, the dates that apply to each, and the four components an SMS is built from. This article walks through the rule section by section and links each part to the current text on eCFR, where it is updated as the FAA amends it.
Who Part 5 lists
As written in 14 CFR 5.1, Part 5 applies to Part 121 and Part 135 certificate holders, holders of a Letter of Authorization under §91.147, and certain Part 21 type and production certificate holders.
The dates in Part 5
Each group in 5.1 has its own section in Subpart A.
- Part 121: 14 CFR 5.7(a) gave operators with an SMS acceptable to the FAA on or before May 28, 2024 until "May 28, 2025" to revise it to meet the current rule.
- Part 135 and §91.147: 14 CFR 5.9(a) sets May 28, 2027 as the date by which operators authorized before May 28, 2024 are to "develop and implement an SMS" and submit a declaration of compliance. Applicants on or after that date come under 5.9(b).
- Production certificate holders that hold or license the type certificate for the same product: 14 CFR 5.11 sets November 28, 2024 for submitting an implementation plan and May 28, 2027 to implement the SMS.
- Type certificate holders applying for a production certificate: 14 CFR 5.13 sets implementation "no later than 36 months after submission of the implementation plan."
14 CFR 5.9(e) also lists sections that "do not apply to those organizations with a single pilot who is the sole individual performing all necessary functions."
The four components
As written in 14 CFR 5.5(a), an SMS "must be appropriate to the size, scope, and complexity of the person's organization" and include safety policy, safety risk management, safety assurance and safety promotion. Each has its own subpart.
| Subpart | Covers | Sections | |---|---|---| | B | Safety policy | 5.21 to 5.27 | | C | Safety risk management | 5.51 to 5.57 | | D | Safety assurance | 5.71 to 5.75 | | E | Safety promotion | 5.91 to 5.93 | | F | Documentation and records | 5.95 to 5.97 |
How operators use the structure
The components describe a loop rather than a checklist. Policy sets who decides and what the organization is aiming for. Risk management finds hazards and decides on controls. Assurance checks whether the controls work. Promotion makes sure people know what was learned. Operators who get value from an SMS run that loop on real decisions, such as a new destination, a new aircraft or a staffing change, rather than treating each component as a document.
Whether Part 5 reaches a particular operation depends on everything that operation holds and does, so that is a question for your FSDO or your principal inspector. To talk through how an SMS would fit yours, book a demo.